Dutch ornamental grower JK Plant has begun preparation and strip-out work at a greenhouse site in Honselersdijk, the Netherlands, as part of a two-stage redevelopment. Around 9,000 m² (0.9 hectares) of existing greenhouse space will be retained and modernised, while a separate 18,000 m² (1.8-hectare) new greenhouse is planned for 2027. Construction of the new structure has not yet started.
VDF Greenhouses, the appointed builder, says the new-build phase is scheduled to start in week 10 of 2027. The sequence is also described in a 20 November interview with JK Plant co-owner Jelle Kuijvenhoven published by BPnieuws, which confirms that initial works have begun.
Modernising the retained 9,000 m² comes first
The project starts with clearing and adapting the acquired greenhouse. Mustang Demolition is removing existing cultivation floors, internal partitions and facade heating, exposing underground water basins as the site is prepared. A1 Group is taking out the previous screen installation so that a new double-screen system can be fitted, according to the grower interview.
VDF Greenhouses is responsible for changes to the roof-ventilation mechanisms and their controls, adjustments to facade sections, new structural members where an internal division was removed, and other refurbishment work. The contractor says a new concrete path will also be installed. Its announced sequence calls for plants to be moved into the retained section before further demolition makes way for the new greenhouse.
Groen Label Kas planned for Monstera and Araucaria
The 18,000 m² new build is intended to accommodate Monstera and Araucaria, two crops already associated with JK Plant’s ornamental-plant business. The grower has chosen a Groen Label Kas design. According to the interview, better insulation is intended to retain heat more effectively and enable wider use of sustainable energy options; no measured energy savings for this planned facility have been reported.
JK Plant currently expects automation equipment to be installed and the redeveloped facilities to enter use around July 2027. That is the grower’s target timetable, not a confirmed commissioning date. The March construction start and July use target both remain dependent on subsequent project execution.
Why the phased project matters
For greenhouse construction and climate-equipment suppliers, the redevelopment combines active refurbishment orders with a defined future building programme. For ornamental growers, the phasing is relevant because it aims to keep part of an existing site in use while older structures are replaced, with upgraded screening, ventilation and production logistics forming part of the investment.
What remains unclear
The project’s total investment, permitting details and net change in productive growing area have not been disclosed in the cited announcements. The proposed 18,000 m² structure should not be counted as completed or operating greenhouse capacity.
Key takeaways
- Preparatory and refurbishment work has begun; the retained greenhouse section covers 9,000 m².
- VDF Greenhouses plans to start the separate 18,000 m² new build in week 10 of 2027.
- JK Plant targets July 2027 for automation and use, but that remains a forecast rather than a verified opening.
Featured photograph: JK Plant’s co-owners in an existing company greenhouse, from the grower’s official photo archive. This is not an image of the current refurbishment or planned new build. Photo: JK Plant.