Varde approves zoning for Selected Group’s first 20ha Ølgod greenhouse phase

Two 10ha greenhouses are proposed next to atNorth’s DEN02 data centre in Denmark. The local plan is adopted, but the building permit, financing close and construction are still ahead.

Architectural rendering of atNorth's proposed DEN02 data-centre campus near Ølgod, Denmark

Varde Municipality has given final local-plan approval for a combined data-centre and greenhouse development near Ølgod, Denmark, clearing a planning milestone for Selected Group’s proposed first 20 hectares of glasshouse production. The decision does not mean the greenhouses have received their separate building permit or that construction has begun.

The municipal council adopted municipal-plan amendment 2 and local plan 24.10.L03 on 6 October 2026. The plan, published on 8 October, allows a development at Krageris linking a data centre with greenhouse horticulture, technical facilities and water management.

First phase covers two 10-hectare greenhouses

In a 14 October project update, Selected Group outlined two planned 10-hectare greenhouses in the first phase. It said land and heat have also been reserved for two additional 10-hectare units, taking the developer’s potential programme to 40 hectares if all stages proceed.

The developer says it has secured a long-term heat-offtake agreement with data-centre operator atNorth, along with land and grid-connection agreements. Heat recovered from atNorth’s planned DEN02 campus is intended to support year-round cultivation, with the greenhouse development progressing alongside the data-centre project. atNorth separately confirmed the municipal planning decision and its role in the linked development.

Building permit and financing are the next tests

Selected Group identifies the greenhouse building permit as its next permitting milestone. It is targeting financial close in December 2026, greenhouse construction in the second quarter of 2027 and a first growing season in the third quarter of 2028. Those dates remain developer plans, not confirmed start or completion events. The crop mix has not been finalised.

AtNorth has outlined a separate potential construction timetable for its data-centre infrastructure; that should not be confused with the greenhouse construction schedule. The municipal planning decision covers the broader integrated site, rather than certifying that either part is operational.

Why the planning decision matters

For greenhouse contractors, heating-system providers and investors, the approval advances a large potential Danish project from the land-use planning stage toward more specific financing, building-permit and procurement decisions. Selected Group points to its operating Frövi greenhouse development in Sweden as experience for the model, but the Ølgod scheme still has several approvals and commercial milestones ahead.

The next concrete signals will be a greenhouse-specific building permit, confirmation of financial close and a documented construction start—not simply further project announcements.

Key takeaways

  • Varde adopted the Krageris local plan on 6 October, enabling planning for an integrated data-centre and greenhouse site.
  • Selected Group proposes an initial 20 hectares, with another 20 hectares reserved as an option; neither area is evidence of completed greenhouse construction.
  • A building permit, financing close and actual greenhouse construction remain the critical next steps.