Business signals for the global greenhouse industry

PROJECTS

NETHERLANDS 2 NOV 2 MIN READ

Axia’s 6,300 m² demo greenhouse completes overhead installations, commissioning still ahead

Certhon says screens, lifting equipment and greenhouse-level heating are installed at Axia's new Naaldwijk demonstration site, with groundwork and system testing to follow.

Photograph supplied by Axia Vegetable Seeds from the July 2026 Experience Center project launch

Construction of Axia Vegetable Seeds’ new demonstration greenhouse in Naaldwijk, the Netherlands, has reached a further technical milestone. Greenhouse builder Certhon said in its 26 October project update that the screening systems, lifting installation and greenhouse-level heating system are now installed. Internal excavation, concrete work and commissioning remain to be completed.

The update distinguishes progress in installing overhead equipment from an operational handover. Certhon says contractors are finishing excavation inside the greenhouse, with subsequent concreting intended to prepare the site for commissioning its technical systems. No completion date or confirmed first production date was provided in the October announcement.

Four demonstration compartments planned

Axia announced the Experience Center’s scope in July: more than 6,300 square metres of greenhouse area split into four demonstration compartments, two with artificial lighting and two without. Plans also include a 700 m² hall and a water basin of approximately 5,000 m³.

The tomato breeding company intends the facility to demonstrate commercial varieties under different cultivation conditions to growers and business partners. Certhon is responsible for a turnkey package covering greenhouse construction and key heating, water and electrical infrastructure. The July announcement targeted first planting at the end of December; that target should not be mistaken for a subsequently verified planting or opening date.

Why the construction stage matters

For buyers of greenhouse engineering and breeding technology, the progress shows that major mechanical packages are moving through installation, while the remaining civil works and commissioning still determine when the site can be used for trials and customer demonstrations. The company has not provided an investment value or validated performance results for the new demonstration site.

Axia also operates a separate research greenhouse completed earlier in 2026; the October construction milestone concerns the newer Experience Center, not the already operational research facility.

Key takeaways

  • Axia’s new demonstration greenhouse covers more than 6,300 m² across four planned compartments.
  • Certhon reports overhead technical installations completed, with excavation, concrete work and commissioning still outstanding.
  • First planting and handover remain future milestones rather than confirmed October outcomes.