Henan greenhouse upgrades worth CNY17.34m move to quality checks

Huaxian County is seeking independent inspection for a five-operator programme covering 19 new greenhouses and 32 upgrades.

Grape cultivation under cover in China; illustrative greenhouse photograph, not a Huaxian 2026 project site

Huaxian County in China’s Henan province has opened a request for quotations for independent quality acceptance work on a greenhouse improvement programme involving five farms and cooperatives. The county agriculture and rural affairs bureau’s notice, published on 2 November 2026, places the programme’s combined self-financed investment at approximately CNY17.34 million.

The announced work covers 19 new protected-growing structures and equipment upgrades to 32 existing greenhouses. These are planned programme allocations; the request for quality-verification services does not itself confirm that construction and upgrades have been completed or accepted.

Five grower-funded investments

According to the official breakdown, Ruiping Family Farm accounts for CNY5.84 million, with two new insulated houses and upgrades to eight older solar greenhouses. Luchuang Planting Cooperative has allocated CNY4.16 million for ten new houses and improvements to 21 existing units.

Haizhong Family Farm’s CNY4.35 million allocation covers demolition of four old structures and construction of six replacement solar greenhouses. Xusheng Cooperative plans one new solar greenhouse under a CNY1.07 million allocation; Desheng Green Vegetable Cooperative plans upgrades to three older houses for CNY1.92 million.

The four houses to be demolished at Haizhong should not be added to the 32 upgrade count. The programme is spread across Baidaokou, Gaoping, Shangguan, Cizhouzhai and Dazhai townships.

Independent checks enter procurement

The bureau is seeking a qualified third-party firm to assess project quality and issue a formal acceptance report. Quotation submissions run from 2 to 10 November, and the selected provider would have 20 days from signing a service contract to finish its work.

For greenhouse suppliers and regional operators, the notice documents the number of houses and the private investment behind a county-level modernisation effort. The outcome of the acceptance checks, the service provider and the exact status of physical works remain to be established.

Key takeaways

  • Five growers and cooperatives account for about CNY17.34 million in self-financed greenhouse works.
  • The official breakdown covers 19 new structures and improvements to 32 existing houses.
  • Huaxian is soliciting independent quality-acceptance services, not announcing a final acceptance result.