A new 33-greenhouse vegetable production project in Duzhai village, Gaoping, in China’s Shanxi province, has progressed to steel-frame installation, according to a 4 November 2026 update from the Gaoping municipal government. Developer Gaoping Wugufeng Agricultural and Rural Investment Group began construction in August and is working toward a high-standard protected-cropping base in Yechuan town.
Officials say crews have installed ground piles across 30 mu (2 hectares) and steel greenhouse frames across 20 mu (about 1.33 hectares). These figures describe construction progress at different stages, not two separate fully operational growing areas. More than 20 workers were reported at the site during the update.
Thirty-three structures planned across a 10.5-hectare site
The municipality gives the project’s total site area as 157.7 mu, approximately 10.51 hectares, and says it will contain 33 greenhouse buildings with all-steel-frame structures. The 10.51-hectare figure is the whole project site, not a confirmed net greenhouse crop area.
Work still ahead includes laying insulation covers, installing greenhouse film and sealing, and adding supporting pipe networks. The announced equipment package also includes smart irrigation, environmental monitoring, pest management and product traceability systems. These are described as planned facilities, not already installed systems.
Once completed and brought into operation, the municipality expects the project to produce approximately 360 tonnes of fresh vegetables annually and create more than 20 local jobs. Neither figure is a current production or employment result. The announcement does not specify a firm completion date.
What the construction stage signals
For greenhouse contractors, suppliers and protected-vegetable operators, the confirmed installation of piles and steel frames is a more concrete project signal than an early planning notice. However, it does not establish when covers, utilities, climate controls or growing systems will be commissioned.
An earlier Gaoping agricultural-bureau funding notice from May 2026 also names Wugufeng and Duzhai, describing a 60-mu solar greenhouse proposal. Its project scope is not directly reconciled with the municipality’s November figure of 157.7 mu. The subsidy described in that notice should not be treated as the total capital cost of the 33-greenhouse development.
What remains unclear
The municipality has not reported confirmed greenhouse-covered area, final construction budget, equipment procurement awards, a commissioning date or binding offtake contracts. Subsequent installation and handover milestones will determine when the planned annual output becomes realistic operating capacity.