ESTONIA 10 NOV 3 MIN READ

Verevi Aed seeks builder for 5,448m² Estonian greenhouse

Verevi Aed's Leie tender calls for a 5,448m² greenhouse with heating, irrigation, shading and automation, with bids due 13 November. An official budget has not been independently verified.

Sunlit commercial greenhouse with rows of tomato plants; illustrative photo, not Verevi Aed or its planned Leie project

Estonian grower Verevi Aed OÜ is seeking a single contractor to build a proposed 5,448 m² (0.54-hectare) production greenhouse with integrated technical systems in Leie village, Viljandi County. Copies of procurement notice RHR 317234 list a 13 November 2026, 13:00 Estonia-time bid deadline and a target date of 31 May 2027 for handover of the completed facility. This remains an open construction procurement, not a contract award or operating greenhouse.

The Riigihanked.eu reproduction of Estonian procurement-register open data identifies Verevi Aed by registration number 12182934 and describes the purchase as one combined construction and technology package. A second Estonian procurement tracker reproduces the scope and deadline. The original government RHR detail was not independently opened, so contractors should verify updates and submission instructions on the official Estonian procurement portal rather than relying only on these mirrors.

Construction and climate systems bundled into one contract

The proposed greenhouse package covers building work and the supply, installation, connection and commissioning of heating, irrigation, fertiliser dosing, ventilation, shading, electrical and automation systems. The buyer already has a boiler house and pellet hopper, according to the reproduced tender text; purchasing those items is expressly outside the requested scope.

That distinction matters for firms assessing how to assemble a bid. The winning contractor would have responsibility for coordinating both the structure and a broad set of growing-environment systems, rather than supplying a standalone greenhouse frame. No equipment manufacturers or selected subcontractors are named in the notice.

A vegetable grower, but the new crop mix is unspecified

The Estonian Horticultural Association’s grower-cluster membership list identifies Verevi Aed as a business involved in vegetable growing. That association record corroborates the buyer’s commercial sector, not the precise crop to be cultivated inside the proposed Leie greenhouse. The tender excerpts do not establish the new facility’s annual output or first harvest timetable.

The procurement copies describe financial support from European Union funding, but the latest award decision and the exact amount payable to the contractor are not established. Some commercial aggregators show an indicative €850,000 figure, while another Estonian procurement listing says the budget was not published. Without a directly verified authority-issued budget, that estimate should not be treated as an official contract ceiling.

What the deadline means for suppliers

For Baltic greenhouse builders and technical integrators, RHR 317234 describes a small but specific turnkey opportunity with a live near-term response window. Its significance lies in the breadth of required controls and irrigation systems per project, not in a large land footprint. The next confirmable signals are deadline amendments, bids, a formal supplier award and evidence that installation has started.

Key takeaways

  • Verevi Aed is seeking one contractor for a 5,448 m² production greenhouse with integrated heating, fertigation, ventilation, shading, power and automation.
  • Procurement copies give 13 November 2026 as the bid deadline and 31 May 2027 as the target handover, but the official portal should be checked for changes.
  • No award, construction start, exact new crop mix or independently confirmed official contract budget has been established.

Featured image: Illustrative commercial tomato greenhouse by Mark Stebnicki / Pexels. It does not depict Verevi Aed’s proposed Leie site; the new facility’s crop is not confirmed.