Rhineland-Palatinate has launched a general-planning tender for the phased replacement of greenhouses at the Johannes Gutenberg University Mainz Botanical Garden in Germany. The competition, published on 4 November 2026 as EU notice 764863-2026, is inviting participation applications until 8 December 2026. It is a design-services procurement, not an award of greenhouse construction works.
The proposed replacement facilities cover approximately 2,360 square metres within an existing botanical garden greenhouse site of about 11,950 square metres, according to the published tender text reproduced by HelloTender. The buyer is the state of Rhineland-Palatinate through its LBB building and property agency, with tender reference 25D0320.
Four phases would keep the botanical garden operating
The scheme calls for staged demolition of ageing greenhouse structures, service lines and ancillary facilities, followed by new public display greenhouses and non-public spaces for research, plant propagation and collections. Planned components include tropical houses, research greenhouses, overwintering facilities, service connections and landscaped areas.
Implementation is described in four partially overlapping construction phases while the garden’s plants, research and visitor operations continue. That constraint makes temporary accommodation, construction logistics and sequencing central to the general planner’s assignment.
The tender seeks multidisciplinary design and coordination covering architecture, structural engineering, building services, external works, thermal performance, fire protection, sustainability and demolition-related management. Specialist designers will therefore need to integrate greenhouse environmental systems with the demands of an operating botanical research collection.
€31.81 million is a provisional works estimate
The notice cites approximately €31.81 million gross in provisional combined construction and landscaping costs under German cost groups 200–600. It does not disclose a €31.81 million fee for the planner, nor does the figure constitute an awarded contract or money already spent.
Indicative procurement milestones place construction contracting in 2029, with works planned across roughly late 2029 to 2033. Those dates remain forecasts subject to planning, approvals and subsequent procurements, rather than confirmed start or completion announcements.
Why it matters for greenhouse suppliers
This is an early opportunity for architectural and engineering consortia capable of coordinating greenhouse envelopes, technical systems and specialist growing environments. Greenhouse constructors and equipment providers can monitor the later design and construction tenders, but the current opening is for general planning, not greenhouse equipment orders.
The botanical garden’s earlier architectural site documentation also describes the ageing dispersed houses and energy losses that motivate its wider renewal programme. That historical context is separate from any selection of a planner under the new 2026 tender.
What remains unclear
No winning general planner or construction contractor has been identified in the current notice. The eventual approved design, final project expenditure and any revisions to the multi-year timetable will require later official decisions and awards.
Key takeaways
- The Mainz university garden seeks a general planner for roughly 2,360m² of replacement greenhouse facilities.
- Applications close 8 December 2026; the four-stage works programme is still provisional.
- €31.81 million is an estimated overall works figure, not the planning contract value.