Authorities in Wengniute Banner, Inner Mongolia, say work is advancing on a CNY 30 million energy-saving greenhouse project at the banner’s modern agricultural demonstration park in Chifeng. A 12 November 2026 progress notice covers 54 planned greenhouses on a site of 127.5 mu (approximately 8.5 hectares).
Construction began in September, according to the Modern Agricultural Industrial Park Service Center. The centre says building and decoration work on the earth-wall greenhouse group is 85% complete; that figure does not describe overall project completion or operational growing capacity.
Five insulated-panel houses and 49 earth-wall greenhouses
The scheme comprises five double-arch, double-film greenhouses with insulation panels and blankets, plus 49 double-arch, double-film earth-wall solar greenhouses with insulating blankets. The disclosed 127.5 mu is the total project site, not a verified area under greenhouse cover.
The stated infrastructure scope includes two 100 m³ stainless-steel water tanks, two 250 kVA transformers, 371.8 metres of electrical conduit, 1,470 metres of 10 kV overhead line and approximately 9,464 m² of paved roads. These figures describe planned or reported works, not greenhouse floor space.
Construction and supporting works
In its November update, the authority reported that earthworks and electrical works for the earth-wall structures had been completed, while building and finishing work had reached 85%. For the insulated-panel structures it reported completion of earthworks, municipal works, demolition, equipment installation and water-supply and drainage works. It also described the park’s water, power and road infrastructure as complete.
The notice records CNY 20.105 million as funds or work completed under the project, but does not make clear from its wording whether that amount represents certified construction value, payments or another accounting measure. It should not be treated as independently verified expenditure.
Why this matters for greenhouse suppliers
The update gives structure builders, insulation suppliers, electrical contractors and water-system providers a more specific picture of a project already under construction, rather than a proposed facility with no reported site activity. The reported progress concerns defined work packages; it does not establish that the greenhouses have been commissioned or started producing crops.
What remains unclear
The notice does not identify a construction contractor or commercial grower, confirm the crop mix, disclose enclosed growing area or set an operational start date. A later handover or commissioning notice would be the next meaningful signal.
Key takeaways
- Wengniute’s CNY 30 million project includes 54 greenhouse structures across an approximately 8.5-hectare site.
- The authority reports 85% progress on the earth-wall greenhouse building and finishing work, not on the entire park.
- Supporting water, power and road works are reported complete; commercial operation has not been confirmed.
Featured image: Illustrative photograph of greenhouse tunnel construction at an unrelated farm; it does not depict the Wengniute project. Photo: Alfo Medeiros / Pexels.