NETHERLANDS 21 NOV 3 MIN READ

Siberia Greenhouse advances 5ha Maasbree expansion as CHP is installed

Siberia's 5ha phase-five greenhouse at Maasbree is under construction. Cogas says its CHP has been installed and connected, but testing and commercial production remain ahead.

Two people above rows of hydroponic lettuce inside Siberia Greenhouse, Maasbree, Netherlands

Siberia Greenhouse is progressing with a five-hectare fifth construction phase at its hydroponic leafy-greens site in Maasbree, the Netherlands. The new glasshouse remains under construction, while technical contractor Cogas Climate Control says a combined heat and power (CHP) unit has been positioned and connected but still awaits final work and testing.

Greenhouse builder Maurice Kassenbouw | Ammerlaan Construction identifies the project as phase five, with five hectares of additional glasshouse space being developed in 2026. The planned growing arrangement again uses an automated mobile-gutter system for leafy vegetables cultivated in water. The contractor describes the phase as in progress, not as a completed, producing greenhouse.

CHP connected, commissioning still ahead

In its latest project progress update, Cogas reports simultaneous work on facades, utility infrastructure and water, electrical and heating installations. The contractor says the CHP, known locally as a WKK unit, has been placed and connected. Remaining work must be finished before it can be tested.

Installation and connection are meaningful construction milestones, but neither confirms that the CHP is operating commercially nor that its power or heat is already being delivered to the new growing space. Cogas’s update also describes ongoing greenhouse systems work; it does not announce a commissioned production line or first harvest from the extension.

Growing-system continuity at an established operator

Siberia already grows lettuce and other leafy vegetables using water-based, mobile-gutter cultivation. Its established system moves the crop through different gutter spacings before harvest and packing. The new phase would extend that form of controlled-environment cultivation, but planned area should not yet be recorded as operating output.

An earlier project account from supplier Servex independently associates a five-hectare expansion at Maasbree with Van Dijck Groenteproducties and the Fossa Eugenia growers’ network. That account provides operator and project context rather than a verified 2026 commissioning date.

Why it matters for greenhouse suppliers

The project represents active demand for greenhouse construction, hydroponic growing systems and energy and climate infrastructure at a named Dutch commercial grower. The CHP installation adds a specific, observable energy-system milestone to the expansion, while the remaining tests and building works are the next steps to monitor.

A completion date, the new phase’s capital cost, CHP operating performance and the start of commercial harvesting have not been established in the available updates. Those details are needed to distinguish construction progress from added productive capacity.

Key takeaways

  • Siberia’s fifth Maasbree greenhouse phase adds five hectares of planned hydroponic leafy-greens growing area.
  • Cogas says the CHP has been installed and connected, with final work and testing still to come.
  • Construction and system installation are continuing; new commercial production has not been confirmed.

Featured photograph: the existing hydroponic lettuce-growing area at Siberia Greenhouse in Maasbree, from an Interpolis company case study. This archival view does not show the 2026 fifth-phase construction or CHP equipment. Photo: Interpolis.