Utility-infrastructure work has begun at the Green Gardens Dobrovnik site near Žitkovci in northeastern Slovenia, moving a long-planned commercial greenhouse development into its first physical enabling stage. The work concerns site services and an electrical connection; construction of the greenhouse structures themselves has not yet been confirmed. The start was marked on 29 October, according to local reporting by Vestnik.
The investor’s first phase is estimated at approximately €74 million, a projected investment rather than verified expenditure or secured financing. Green Gardens Dobrovnik’s project website specifies 3.2 hectares of planned greenhouse growing area for baby-leaf salads, alongside automated preparation and packing facilities. It projects more than 50 jobs and initial production toward the end of 2027.
Utilities come before the greenhouses
Prlekija-on.net reports that crews are preparing utility infrastructure and the power connection for a development planned in four phases across roughly 22 hectares of land. Greenhouse buildings, energy installations and storage facilities are intended to follow these enabling works. The entire site area should not be confused with either the first-phase cultivation area or completed greenhouse capacity.
The current investor plan includes water recirculation, rainwater and groundwater use, biomass-based combined heat and power, solar generation and battery storage. Geothermal energy is described on the official project website as an option for a later phase, not as a system already operating at the site.
Why it matters
Starting the utility works is a more concrete milestone than another project announcement. For greenhouse engineering, energy-system and automation suppliers, it identifies a development that may generate future equipment and construction demand, although no specific supply awards are established by these reports. For buyers of fresh produce, the proposed first phase could add domestic baby-leaf supply only if the buildings, services and production systems are completed and commissioned.
What remains unclear
The status of permits specifically for the greenhouse buildings, the financing and contracted portion of the €74 million estimate, and the timetable for broader grid upgrades remain material uncertainties. Vestnik reported in May that permitting and electricity-network capacity had delayed the project. The owner’s 3.2-hectare first-phase cultivation figure also differs slightly from the approximately 3.4 hectares cited in some recent local coverage; neither figure represents built growing area.
Key takeaways
- The verified October milestone is site utility preparation, not completion of a greenhouse.
- Green Gardens plans 3.2 hectares of baby-leaf growing space in a first phase estimated at around €74 million.
- Construction permits, financing and electrical infrastructure remain important signals to monitor before the late-2027 production target.
Featured photograph: Green Gardens Dobrovnik project briefing in June 2024, an archival image rather than the October 2026 utility works. Photo: Sobotainfo / Netmedia.