A new procurement notice in China’s Hubei province is seeking an engineering, procurement and construction (EPC) contractor for a planned 390-mu (approximately 26-hectare) greenhouse complex in Huangtan town, Yingcheng. The official tender published on 19 October 2026 gives an estimated contract value of CNY 171.34 million and sets the bid deadline for 11 November.
The invitation is a construction procurement milestone, not an award or evidence that site work has started. Yingcheng Xinyuan Construction Investment Co., Ltd. is the named project owner and procuring entity; Hubei Zhonghui Project Management Co., Ltd. is the tender agent. The project is stated to have received approval from the Yingcheng Development and Reform Bureau.
Three greenhouse formats across 390 mu
According to the tender, the proposed protected-growing structures comprise one fully environmentally controlled intelligent greenhouse covering 50 mu (about 3.3 hectares), 13 large-span solar arch greenhouses covering a combined 180 mu (12 hectares), and 23 winter-warm solar greenhouses covering 160 mu (about 10.7 hectares). Those figures describe the planned greenhouse structures, not a confirmed cultivated or productive area.
The scope also includes electrical installations, water supply and drainage, intelligent control systems, approximately 12,957 square metres of agricultural access roads and 2,000 metres of fencing. Under the EPC structure, the appointed contractor would be responsible for design, equipment and materials purchasing, construction, acceptance, handover and warranty obligations.
Bids close in November; delivery remains prospective
Tender documents are available through Hubei’s electronic bidding platform from 20 to 26 October. Encrypted electronic bids must be submitted by 09:00 China time on 11 November 2026. The notice permits consortium bids, subject to stated design and construction qualifications and experience requirements.
The planned works period is 548 calendar days, with an indicative start date of 30 November 2026. The published CNY 171.34 million is a contract estimate, not a signed agreement, disbursement or confirmed final investment cost. The tender identifies government funding as the source, including central/provincial subsidies and municipal investment.
What suppliers can track next
The tender offers greenhouse contractors, structural suppliers and climate-control integrators a defined prospective procurement opportunity with a documented equipment mix and timetable. It does not identify a winning contractor or committed technology supplier, and the actual crop mix is not specified. The next independently checkable milestone is the bid result, followed by any confirmed construction start.
Key takeaways
- Yingcheng has opened EPC procurement for approximately 26 hectares of planned protected-growing structures.
- The CNY 171.34 million figure is a tender estimate; no contract award is established by the notice.
- Bids close on 11 November 2026, while the proposed construction start is 30 November.