Datong’s Yunzhou ecology bureau has opened public comment on a proposed environmental impact assessment (EIA) decision for the planting component of Huinong Modern Agricultural Science and Technology Park Phase II in Shanxi, China. Its official notice, published on 23 October, specifies a comment period of 22–28 October 2026. The notice concerns a proposed decision, not the issuance of final environmental approval.
The filing identifies Datong Yunzhou District Huinong Modern Agricultural Development Co. as developer, with the cultivation site near Xiaofangcheng and Tuofang villages in Xiping township, Yunzhou District.
Production space differs from total site area
The proposed planting site covers approximately 129,586 square metres (12.96 hectares), including 90,690.8 square metres of building area and 88,115.6 square metres (8.81 hectares) designated as production area. These are three different measures: the production area should not be interpreted as 8.81 hectares of glass-covered growing space.
The authority’s project description lists two intelligent glass greenhouses, three solar greenhouses, three arched growing structures and two multispan greenhouses. It also includes a sorting and packing facility, a control centre and associated structures. The figures describe the scope in the EIA filing, not measured output from an operational expansion.
Heating and wastewater infrastructure are part of the review
For winter heating, the filing specifies a 10-tonne-per-hour natural-gas boiler with low-NOx combustion equipment. Its operating-phase water plan includes a proposed treatment system rated at 500 cubic metres per day for combined irrigation-return, boiler and water-softening waste streams before discharge. Those are planned engineering provisions, not evidence that the systems have been commissioned.
The EIA milestone is separate from construction progress
The regulator recorded receipt of the project’s EIA documents on 4 September. Separately, reporting by the Yunzhou District Media Centre in March described greenhouse steel-frame construction already under way. The October notice is therefore a new environmental-review milestone, not a claim that building work has only just begun.
For greenhouse contractors, heating-system suppliers and water-treatment providers, the notice puts specific infrastructure requirements and an active regulatory decision point on the record. The authority has not established a final EIA outcome in this notice; that decision, rather than the 28 October comment deadline itself, is the next regulatory development to watch.
Key takeaways
- Datong’s proposed EIA decision is open for comment through 28 October 2026, without confirming final environmental approval.
- The planting component lists 8.81 hectares of production area within a 12.96-hectare site and ten greenhouse structures.
- The filing specifies planned gas-fired heating and 500-cubic-metre-per-day wastewater treatment, while the final EIA outcome remains pending.